Vallata Hospital, Genoa, Italy

 
Key Data:
New construction dimensions
23,349m²
ASL district
4,359m²
Machinery room
1,955m²
Land area
38,019m²
Covered area
14,146m²
Cost
€70 million
Public contribution
€49 million
Private contribution (owner equity and loan)
€21 million
Project Timeline:
Call for bidders
30 July 2003
Award of contract
30 November 2003
Commencement of works
15 July 2004
Completion
1 January 2008